Winter Springs Eyes Eminent Domain for Wastewater Plant Replacement

WINTER SPRINGS, Fla. – Winter Springs city commissioners are preparing to vote on using eminent domain to acquire 10 acres at the former Winter Springs Golf Club property for construction of a replacement West Water Reclamation Facility.

The existing wastewater plant has reached the end of its useful life. Replacing it is considered necessary to preserve dependable treatment service and comply with future regulatory standards. The proposed facility would process 1.6 million gallons of wastewater daily, with infrastructure designed to support advanced treatment in the future.

Three alternatives considered

City officials reviewed three possible development plans, weighing construction costs, logistical challenges and the potential effects on the surrounding community.

Alternative 1 would keep all construction within the current facility’s footprint. Although it would avoid the need to acquire additional property, the plan presents the greatest construction and operational risks because of the limited space, extensive phasing and reliance on temporary facilities. The estimated cost is $72.8 million, making it the most expensive option, with completion expected to take about 47 months.

[WATCH: Winter Springs boil water precaution advisory could last through Saturday]

Alternative 2 would require the city to acquire about 3 acres of neighboring land, moving some stormwater storage away from the primary site. That would ease several complications associated with the first plan, but significant coordination and construction-sequencing challenges would remain. The estimated cost is $73.1 million, including environmental mitigation, and the project would take roughly 35 months.

Alternative 3 would involve acquiring approximately 10 acres of adjacent property. The expanded site would allow most new construction to occur away from the operating plant, substantially reducing construction risks and scheduling difficulties. It also offers the fastest projected completion time, at 29 months, and the lowest estimated cost: $66.6 million, including mitigation.

Recommended option

Alternative 3 was selected as the preferred plan despite its larger environmental footprint. Engineers and city planners determined that its lower risk, reduced cost and shorter construction schedule provide the strongest long-term solution for the city’s wastewater system and justify the additional environmental mitigation required at the outset.

Eminent domain as last resort

Commissioner Victoria Bruce said the city attempted to negotiate a purchase with the property owner but was unsuccessful, leaving eminent domain as Winter Springs’ most viable remaining option.

“A purchase would have had to occur, which was outrageous, the amount the landowner wanted to get to be able obtain 10 to 20 acres,” Bruce said. “This is the best course of action. I’ve been advocating for eminent domain since I got into office in 2022.”

Commissioners are scheduled to vote on a resolution launching the eminent domain process during their next meeting Monday at 6:30 p.m.